Project Description

Owner PT. Berau Coal
Handover Location Gurimbang Mine Operation, East Kalimantan
Term of Work 1 (one) August 2023 to 31 (thirty-one) December 2023
Bank Guarantee Advance Payment Bond & Peformance Bond
Warranty 180 (one hundred and eighty) after the work is completed

Scope Of Work

Calculation and Engineering Design 100%
Dismantle dan Re-erection Storage Tank 1x500 KL 100%
Civil Works (Piling, Foundation, Bund Wall and Perimeter Fence) 100%
Pipework & Fire Fighting Systems 100%
Electrical, Lighting and Lightning Protection System 100%
Painting, Testing & Reporting 100%