Construction Storage Fuel Tank 2.000 KL

Artikel Terkait

Kategori

Bagikan

Memiliki Tantangan Teknis Serupa?

Diskusikan kebutuhan EPC dan rekayasa teknis fasilitas Anda bersama tim ahli kami. Kami menjamin eksekusi yang presisi, aman, dan efisien berstandar global.

Project Description

Owner PT. Marunda Grahamineral
Handover Location Jamut, Laung Tuhup, Murung Raya, Central Kalimantan
Term of Work 14 February 2020 and completed 24 October 2020
Bank Guarantee Advance Payment Bond & Peformance Bond
Warranty 365 (three hundred and sixty-five) calendar days after the work is completed

Scope Of Work

Calculation and Engineering Design 100%
Civil Works (Bore Pile, Foundation, Bund Wall and Perimeter Fence) 100%
Fabrication Storage Fuel Tank 2.000 KL 100%
Pipework & Fire Fighting Systems 100%
Electrical, Lighting and Lightning Protection System 100%
Painting, Testing & Reporting 100%

Jelajahi Proyek Serupa

Repair & Improvement Storage Tank 2.000 KL & 2.00 KL

Repair and Improvement Storage Tank 1×3.500 KL

Repair and Improvement Storage Tank 1×5.000 KL