Construction Storage Tank 5.000 KL & Supporting Facilities

Project Description

Owner PT. AKR Corporindo Tbk
Handover Location JI. Trikora, Handil Bakti, Samarinda, East Kalimantan 75251
Term of Work 270 (two hundred seventy) calendar days
Bank Guarantee Advance Payment Bond & Performance Bond
Warranty 12 (twelve) months after the work is completed

Scope Of Work

1. Design Engineering
On Progress
2. Preparation Work for New Area
On Progress
3. Civil Infrastructure Construction
On Progress
4. New Tank Construction
On Progress
5. New Pipeline
On Progress
6. Painting, Testing & Reporting
On Progress